Connect with us

NEWS

Water line problems on two separate lines stall traffic at Pecan and Mason

Published

on

Traffic at the intersection at Pecan and Mason Street was interrupted for two days this week as repairs were made to separate line breaks.
Thursday evening the 12-inch water line that goes to the water tower cracked and a portion of the line had to be replaced. The crew worked late into the night and were able to isolate it so few customers were without water during this period. They were also lucky to find the necessary 12-inch clamps in nearby Decatur.
The hole was left open to make sure it did not leak. After that was completed a leak was found in a valve on a nearby four-inch line in the intersection. They began repairs on it once the lines were spotted and the Texas Department of Transportation was informed about the closure which is a state highway.
City Manager Bert Cunningham said the on-going dry conditions which also causes the ground to shift are the primary causes of the leaks the staff has been repairing in recent weeks.
Utility woes continued for the Bowie area Friday morning as Comcell reported a major network internet outage. A storm in Wichita Falls Thursday night knocked down its main network operations center along with a loss of power about 9 p.m. Service was restored to Bowie shortly before 11 a.m. on Friday.

City water crew worked in water as they tried to repair a split in a 12-inch water line on Pecan Thursday. While repaired with a new section of line and clamps, the hole has been left open to make sure there are no leaks, so the block of Pecan from Smythe to Mason is closed. (Courtesy photo)
Continue Reading

NEWS

Bowie Council accepts phase two sewer line bid

Published

on

By BARBARA GREEN
[email protected]
The Bowie City Council accepted a $1.38 million bid for phase two of the sewer line replacement program and received an engineer’s update on Nelson Street drainage.
Council members met Monday night and opened the evening with the presentation of proclamations for Emergency Medical Services Week and National Travel and Tourism Week. Members of the Bowie EMS service accepted the first proclamation and Cindy Roller of Bowie Community Development accepted the second.
City Manager Bert Cunningham reported the city received one bid for phase two of the sewer line project that will replace the Glenn Hills lift station and sludge pumps at the wastewater plant. While the bid came in above the original estimate, Mike Tibbetts of Hayter Engineering, said there are several things that can be removed to lower the costs.

Read the full story in the weekend Bowie News.

Pictured – replacing a manhole in phase one. (Courtesy photo)

Continue Reading

NEWS

Bowie budget revenues not meeting projections

Published

on

By BARBARA GREEN
[email protected]
In its six-month financial report for fiscal 2024-25 Bowie City Council members saw budget revenues were not coming in as high as projected, despite the budget using conservative figures.
During the Monday meeting, Finance Director Pamela Woods reviewed the numbers at the half-way point of the year. She said all the department heads are doing well keeping their expenses within budget just below the 50% level or 49.26% overall. Despite that, expenses are above revenues in the utility fund by almost $100,000.
In the utility fund revenues are 46.11% of budget in water; 53.19% in sewer and 43.74% in electric. The total utility fund revenue is at 46.42% of the budget or $5,572,694.

(Pictured above) Carol Moore also addressed the council on disrepair at the Pelham Park walking track urging it to make repairs and maintain it.

Read the full council story in the weekend Bowie News.

Continue Reading

NEWS

Chain-reaction crash in work zone injures two

Published

on

Two people were transported to the hospital with possible injuries from a three-vehicle crash Tuesday afternoon in a highway department work zone on State Highway 59.
The accident occurred on Hwy 59 near Allison Road at 4:09 p.m. on May 14. There were three vehicles containing a total of six people.
Vehicle one driven by Carlin Jaster, Bowie with his passenger Zana Lara, Bowie, were traveling south on Hwy. 59. Two other vehicles driven by Kjersti Compton, Sunset and Edward Meadows, Grapevine were also southbound but stopped in a construction zone.
Jaster failed to control his speed and a chain-reaction crash occurred as he struck Compton who then hit Meadows.
Jaster and Lara were transported to Nocona General Hospital with non-incapacitating injuries. The others were uninjured. Tuesday was the first day for road construction along State Highway 59. Digital signs were posted for delays.

(Pictured above) Bowie Rural Fire Department and Bowie EMS responded to this three-vehicle chain reaction crash on State Highway 59 near Allison Road on Tuesday afternoon. There were a total of six people in the three vehicles, and two were transported to Nocona General with possible injuries. (Courtesy photo)

Continue Reading
Ad
Ad
Ad
Ad
Ad

Trending