Connect with us

NEWS

Water crews worked all night to get water flowing again

Published

on

After almost three days under a boil order plus nearly 10 hours without water, City of Bowie water customers saw the boil water order lifted shortly after noon Thursday.
The major line breaks occurred shortly before 3 p.m. on Tuesday when an eight-inch water main blew out in the construction area at Nelson and Mill. City Manager Bert Cunningham said there was an eight-inch line and a six-inch line coming into that line, which had been uncovered during the construction project. All the lines in this area are being replaced in the drainage project.
The CM said with the lines being opened the contractor had struck them a couple of times requiring a fitting and a clamp; however, being uncovered the cast iron line just collapsed due to the weight. There were not working in that area when it occurred.
“Years ago when these lines were put in there were no valves put into them, which would allow you to shut off a section for repair and allow the system to continue flowing. There were no valves, but the new lines will have three. The tower began to drop quickly because we couldn’t turn it off,” explained the manager.
In order to replace the broken section of line, the entire water system had to be shut down, and per the Texas Commission on Environmental Quality any time the system drops below 32 pounds of pressure there is potential for bacteria and a boil order is required. Three consecutive days of clear water tests are required to lift the order.
City water crews worked far into the night Tuesday and Wednesday morning repairing the line, and they thought it was done shortly before 1 a.m., but when it was pressured up, it had to be redone. It was about 3 a.m. before the system was able to start refilling the tower and pressuring up the system. Wednesday morning water was back up and running, with the boil order in place.
Emergency drinking water was provided and available for pick-up at the city fire hall.

Continue Reading

NEWS

Bowie Council accepts phase two sewer line bid

Published

on

By BARBARA GREEN
[email protected]
The Bowie City Council accepted a $1.38 million bid for phase two of the sewer line replacement program and received an engineer’s update on Nelson Street drainage.
Council members met Monday night and opened the evening with the presentation of proclamations for Emergency Medical Services Week and National Travel and Tourism Week. Members of the Bowie EMS service accepted the first proclamation and Cindy Roller of Bowie Community Development accepted the second.
City Manager Bert Cunningham reported the city received one bid for phase two of the sewer line project that will replace the Glenn Hills lift station and sludge pumps at the wastewater plant. While the bid came in above the original estimate, Mike Tibbetts of Hayter Engineering, said there are several things that can be removed to lower the costs.

Read the full story in the weekend Bowie News.

Pictured – replacing a manhole in phase one. (Courtesy photo)

Continue Reading

NEWS

Bowie budget revenues not meeting projections

Published

on

By BARBARA GREEN
[email protected]
In its six-month financial report for fiscal 2024-25 Bowie City Council members saw budget revenues were not coming in as high as projected, despite the budget using conservative figures.
During the Monday meeting, Finance Director Pamela Woods reviewed the numbers at the half-way point of the year. She said all the department heads are doing well keeping their expenses within budget just below the 50% level or 49.26% overall. Despite that, expenses are above revenues in the utility fund by almost $100,000.
In the utility fund revenues are 46.11% of budget in water; 53.19% in sewer and 43.74% in electric. The total utility fund revenue is at 46.42% of the budget or $5,572,694.

(Pictured above) Carol Moore also addressed the council on disrepair at the Pelham Park walking track urging it to make repairs and maintain it.

Read the full council story in the weekend Bowie News.

Continue Reading

NEWS

Chain-reaction crash in work zone injures two

Published

on

Two people were transported to the hospital with possible injuries from a three-vehicle crash Tuesday afternoon in a highway department work zone on State Highway 59.
The accident occurred on Hwy 59 near Allison Road at 4:09 p.m. on May 14. There were three vehicles containing a total of six people.
Vehicle one driven by Carlin Jaster, Bowie with his passenger Zana Lara, Bowie, were traveling south on Hwy. 59. Two other vehicles driven by Kjersti Compton, Sunset and Edward Meadows, Grapevine were also southbound but stopped in a construction zone.
Jaster failed to control his speed and a chain-reaction crash occurred as he struck Compton who then hit Meadows.
Jaster and Lara were transported to Nocona General Hospital with non-incapacitating injuries. The others were uninjured. Tuesday was the first day for road construction along State Highway 59. Digital signs were posted for delays.

(Pictured above) Bowie Rural Fire Department and Bowie EMS responded to this three-vehicle chain reaction crash on State Highway 59 near Allison Road on Tuesday afternoon. There were a total of six people in the three vehicles, and two were transported to Nocona General with possible injuries. (Courtesy photo)

Continue Reading
Ad
Ad
Ad
Ad
Ad

Trending