Nelson Street drainage project delayed once again
By BARBARA GREEN
editor@bowienewsonline.com
Just when everyone thought there was light at the end of the tunnel on the Nelson Street drainage project, City Manager Bert Cunningham said new problems arose last week and the contractor also asked for the rain days reportedly owed per the contract.
In the works for almost a year and closing a major thoroughfare at the same time, the city council was updated at its Monday night meeting. The city manager said it was found the culverts that run from Houston Street to the drop box at Mill and Nelson and from the drop box to the bridge culverts have come loose and must be repaired before any more work can be done at the intersection.
Also, the drop box does not have the correct elevation so water will not enter the drop box under normal rainfall circumstances. Cunningham said problems with the drop box continue to be a sore point after previous questions on incorrect soil compaction that also caused delays.
“The project will not be finished until the contractor gets everything fixed at the box and concrete is poured at the intersection. There are other items that need to be addressed, but the drop box is our main concern,” said the manager.
Read the full story in your weekend Bowie News.
Pictured above: Concrete pour on Nelson Street back in July. Courtesy photo
The Bowie News office will be closed Thursday and Friday for the Thanksgiving holiday.
NEWS
One call made the McBride family whole
Perhaps no loss feels quite as devastating as that of a child. Clint and Shari McBride found this out through their own tragedy.
The McBrides had their son Preston in 2000. Between 2001 and 2007, the couple experienced four pregnancy losses, including an especially devastating miscarriage six months along in 2007.
“I just kept thinking, ‘Oh, I’m going to get pregnant. I’m going to get pregnant.’ I never did,” Shari said. “Ten years later, looking at that test every month, I was so tired.”
In 2011, after a decade of heartbreak, the McBrides decided to take a period of reflection.
Read the McBrides full story in your Thursday Bowie News.
NEWS
Town hall updating citizens
Residents will get a look at the draft direction of Bowie’s comprehensive plan during a second public town hall announced by city officials.
The City of Bowie will host Town Hall #2 from 5:30 to 7 p.m. on Nov. 30, at Community Center East Hall. The session is set to pair a presentation on the draft plan with an open house featuring interactive maps.
Officials say the goal is to give residents a chance to review proposed direction and share feedback on land use, housing, infrastructure and community priorities.
Read the full story in your Thursday Bowie News.
-
NEWS3 years agoSuspect indicted, jailed in Tia Hutson murder
-
NEWS4 years agoWreck takes the life of BHS teen, 16
-
NEWS3 years agoMurder unsolved – 1 year later Tia Hutson’s family angry, frustrated with no arrest
-
NEWS4 years agoSO investigating possible murder/suicide
-
NEWS4 years ago2 hurt, 1 jailed after shooting incident north of Nocona
-
Show us something good9 years agoCountry music star children perform in Bowie
-
100th Birthday4 years agoLooking back at the 1958 Centennial edition of The Bowie News
-
Show us something good9 years agoBowie finally earns ‘World’s Largest Bowie Knife” record from Guinness